Nelividi LIS on back water of Ramanpadu Balancing Reservoir


Vice Chairman & Managing Director, APSIDC Ltd., has submitted an estimate for the work “Construction of Nelividi L.I. Scheme on Back Water of Ramanpadu Balancing Reservoir near Nelividi Village, Kothakota Mandal, Mahabubnagar District” stating that administrative approval for Rs.1130.47 lakh for Nelividi L.I. Scheme with SSR 2006-07 was accorded vide G.O.Ms.no. 225, dated 19.12.2006 under NABARD – RIDF – XII to create an I.P. of 3100 acres. The other details of the scheme are the following. Technical sanction has been accorded for Rs.1130.37 lakh under NABARD/RIDF-XII. Works were grounded and almost all the works have been completed and it is ready for trial run. The work was awarded to Sri K. Bala Narasimha Reddy, Hanamkonda, excluding distributory system of minors.  All agreement works completed and the scheme commissioned in 03/2012.  For minor distribution system for stage – I & II, the work laying of three sub gravity mains for a length of 1.33 Km is grounded in 7/2012 and after completion, another 400 acres of ayacut can be irrigated.  Hence ‘Gravity Mains of PVC / RCC pipes and RCC Intermediate Distribution Chambers’ for Rs.528.00 lakh are proposed to serve total ayacut of 3100 acres. Further, he has stated that the quantities for earth work in excavation for gravity mains and sub-gravity mains etc., are more than 1000 cum having a depth of excavation more than 2 m. Hence, such works could not be taken up manually. Hence, he has requested to accord revised administrative approval for Rs.1638.31 lakh (i.e., Rs.1130.31 lakh actual expenditure incurred + Rs.528.00 lakh) for the subject work under Normal State Plan.

View Larger Map

Government after careful examination of the matter hereby accord revised administrative approval for Rs.1602.40 lakh (Rupees sixteen crores two lakhs and forty thousand only) (i.e., actual expenditure incurred Rs.1110.31 lakhs and now sanctioned an amount of Rs.492.09 lakhs for proposed additional works) for the work “Construction of Nelividi L.I. Scheme on Back Water of Ramanpadu Balancing Reservoir near Nelividi Village, Kothakota Mandal, Mahabubnagar District”.

The amount of Rs.492.09 lakh (Rupees four crores ninty two lakhs and nine thousand only) sanctioned at para 2 above shall be debited to   the Head of Account “4702 – MH 101 – Surface Water – GH (11) Normal State Plan – SH (15) Lift Irrigation works – 530 Major Works – 531 other expenditure”.

The Vice Chairman & Managing Director, APSIDC Ltd., shall take necessary action accordingly to complete the work within the stipulated period without fail and furnish utilization certificate to the Government.

This order issues with the concurrence of Finance (Expr. PW-I) Department vide their U.O. No. 28894/699/Expr. PW (I)/13, dated 20.11.2013.
G.O.Rt.no: 1140 Dated: 28.11.2013

1. From the Vice Chairman & Managing Director, APSIDC Ltd, Hyderabad, Letter. No. IDC /MD /Tech /DEE-2/ Nelividi LIS/ 2011-12 /4707, dated 10.02.2012
2.    From the Vice Chairman & Managing Director, APSIDC Ltd, Hyderabad, Letter. No. IDC/MD / Tech/ Mahabubnagar/ Nelividi LIS/2012-13 /2769, dated 06.10.2012
3.    From the Vice Chairman & Managing Director, APSIDC Ltd, Hyderabad, Letter. No. IDC/MD / Tech/ Mahabubnagar/ Nelividi LIS/2012-13/4966, dated 22.03.2013
4.    From the Vice Chairman & Managing Director, APSIDC Ltd, Hyderabad, Letter. No. IDC/MD /Tech/Mahabubnagar/ Nelividi LIS/2012-13/271,    dated 20.04.2013
5.    From the Vice Chairman & Managing Director, APSIDC Ltd, Hyderabad, Letter. No. IDC/MD/Tech/Mahabubnagar/Nelividi LIS/2013-14/1440, dated 09.07.2013.
6.    From the Vice Chairman & Managing Director, APSIDC Ltd, Hyderabad, Letter. No. IDC/MD / Tech/ Mahabubnagar/ Nelividi LIS/2013-14/1552, dated 19.07.2013