Sammakka Saralamma Jathara February 2014 – 2035 Lakhs


The Engineer-in-Chief (I), Hyderabad sent an estimate prepared by the Superintending Engineer, Irrigation Circle, Warangal an estimate for “Construction of Bathing Ghats and other amenities for Sammakka Saralamma Jathara – 2014, Medaram (V), Thadvai (M), Warangal District” for Rs.2065.00 lakh for according Administrative approval. As per the report of the Superintending Engineer, Irrigation Circle, Warangal the estimated pilgrims would be about 80 to 90 lakh and keeping in view the problems faced during previous Jathara, 1190 m of new bathing Ghats are proposed at U/S, L/S of Road Bridge near Kothur, and D/S R/S R&B Road Bridge near Oorattam &Oorattam cause Way to Chilukalagutta.

The Engineer-in-Chief (I), Hyderabad has also requested the Government to accord administrative approval for the above work “Construction of Bathing Ghats and other amenities for Sammakka Saralamma Jathara, February, 2014, Medaram (V), Thadvai (M), Warangal District” for an amount of Rs. 20,56,95,000/-.

Sammakka Saralamma Jathara February 2014

Government of AP after careful examination of the above proposal, hereby accord administrative sanction for the work “Construction of Bathing Ghats at U/S, L/S of Road Bridge near Kothur, and D/S R/S R&B Road Bridge near Oorattam &Oorattam cause Way to Chilukalagutta and other amenities for Sammakka Saralamma Jathara, February, 2014, Medaram (V), Thadvai (M), Warangal District” for an amount of Rs. 2035.80 lakh (twenty crore thirty five lakh and eighty thousand only). In view of the short time available for the commencement of the Sammakka Saralamma Jathara – 2014, the works pertaining to the construction of the Bathing Ghats be taken up in two phases i.e., 50% during the current year 2013-14, and the balance 50% in 2014-15. Tenders in the first stage shall be limited to 50% of the amount of Rs.20.3580 Crore.

The Expenditure sanctioned in para (3) above, shall be debited to the Head of Account “4711 – COL –on – FCP – 01 –FC –MH-103 – Civil Works –GH11 – NSP –SH (05) Embankments – 530 Major works – 531 other expenditure”

The Engineer-in-Chief (I), Hyderabad shall take necessary action in the matter, accordingly.

This order issues with the concurrence of Finance (Expr.PW-I) Department vide their U.O.No.27037/645/Expr.PW.I/2013, dated:30.10.2013.

G.O.Rt.No. 1111 Dated 20 November, 2013

From the ENC (I), Hyderabad, Lr.No.ENC(I)/DCE IV/OT7/SO2/ Medaram/ 2013, dated:04.10.2013.

Construction of Bathing Ghats and other amenities for Sammakka Saralamma Jathara, February, 2014, Medaram,  Thadvai,  Warangal  District Telangana State