Under the circumstances reported by the Commissioner, Planning & Development of Godavari Basin, Hyderabad, in the references 1st to 7th read above, Government after careful examination of the proposal, hereby accord Administrative Approval for an amount of Rs.320,55,600/- (Rupees Three Hundred and Twenty Lakhs, Fifty Five Thousand and Six Hundred Only) for the work of “Construction of DLB across Koulasanala River between Donegaon and Shakthinagar on U/S of Koulasanal Project in Jakkal(M), Nizamabad District,” subject to conditions, to take necessary action on the request of Engineer-in- Chief (R&B), Hyderabad to maintenance (a) proper slope on the approach slab (b) to construct side drains along the road up to the nearest cross drainage structure. Further, he is also requested to obtain approved drawings from CE/CDO duly furnishing the site conditions before according Technical Sanction.

2. The above estimate is chargeable to the head of “4701-Major and Medium Irrigation-03 Medium Irrigation-MH 112 Upper Koulasanala Project”.

3. The Commissioner, Planning & Development of Godavari Basin, Hyderabad, shall take necessary action accordingly.

4. This order issues with the concurrence of Finance (Expr.PW.I) Department vide their U.O. No.27963/681/Expr.PW (I)/13, dated:
13-11-2013.

Irrigation & CAD Dept., – Nizamabad District- Koulasanala Project- Administrative approval for an amount of Rs.320,55,600/- for the work of “Construction of DLB across Koulasanala River between Donegaon and Shakthinagar on U/S of Koulasanal Project in Jakkal(M), Nizamabad District.” – Administrative Approval – Accorded- Orders- Issued.
IRRIGATION & CAD (PW: M&MI (T-II) DEPARTMENT
G.O.Rt.No. 786   Dated:03-12-2013

1. From the Hanmanth Shinde, Jukkal, Constituency, Nizamabad
Dist., of A.P., Lr.No.Nill, dated:22-11-2012.
2. Form the Commissioner, (R&R) Director & Ex- Officio Joint
Secy to Govt., secundrabad, Lr.No.1830/CRR/SS/2012, dated:
24-01-2013.
3. Form the Commissioner, P&D of G.B,Hyd, Lr.No.Comm/GB/ DCE/OT2/13513/Vol.I/2013/831, dated:02-07-2013.)
4.Form the ENC (P.R), Hyd, Lr.No.W3/DEE2/Koulasanala Project
/2013, dated:24-06-2013.
5.  Form the ENC (R&B)), Hyd,Lr.No.31019/EE(T)/DEE6/AEE3/
12, dated:03-11-2012.
6.Form the ENC (Med.Irr), Hyd, Lr.No.ENC/Med/DCEIII/OT2/AEE
/Koulasanala Project, dated:14-02-2013.
7. From the Commissioner, P&D of Godavari Basin, Hyderbad.Lr. No.Comm   /GB/DCE/OT2/13513/Vol.1/2013/1269,   dated
27.09.2013.