Additional Reservoir on Upstream side of Tungabhadra River


Government of Andhra Pradesh after examination hereby accord administrative approval for the work “Detailed Investigation for formation of Additional Reservoir on Upstream side of Kotla Vijaya Bhaskara Reddy Barrage across Tungabhadra River near Gundrevula/Rangapuram Village, C.Belagal (M) of Kurnool District for a total storage of 15.000 to 20.000 TMC including Construction of Spillway, Sluices, Preparation of Detailed Project Report” with a cost of Rs.54.95 Lakhs (rupees fifty four lakhs and ninety five thousand only) as per the details annexed to this order, subject to the following conditions:-

i)   the  investigation  shall suggest  alternatives  i.e.,  reducing  the  number  of villages which are going to be submerged by reducing the storage capacity;

ii) the  Detailed  Project  Report  shall  include  areas  that  can  be  served  in Mahabubnagar and Kurnool Districts.

The expenditure sanctioned in Para (1) above shall be debited to the Head of Account  “‘4700  Capital  Outlay  on  Major  and  Medium  Irrigation  –  01  MI  – Commercial – MH 109 KCC – GH 11 – NSP – SH 27 Canals and Distributories – 530 Major Works – 531 Other Expenditure”.

The Chief Engineer (P), Irrigation, Kurnool shall take further necessary action accordingly.

This order issues with the concurrence of Finance (W&P) Department vide their U.O.No.2214/F5(A1)/13-1, dated:02.07.2013.

1. From the Chief Engineer (P), Irrigation, Kurnool, Lr.No.CE(P)/KNL/ DEE.1/AEE3/Gundrevula/36Govt., dated:22.02.2013.

2. From the Chief Engineer (P), Irrigation, Kurnool, Lr.No.CE(P)/KNL/ DEE.1/AEE.3/Gundrevula/Camp-HYD, dt.20-08-2013.

formation of Additional Reservoir on Tungabhadra River

Annexure to G.O.Ms.No. 100 , I&CAD(M&MI-R.III.1)Department, dated:01.11.2013.

NAME OF WORK:- Conducting Detailed Investigation for formation of additional reservoir on upstream side of Kotla Vijaya Bhaskara Reddy Barrage across Tungabhadra River near Gundrevula / Rangapuram Village, C.Belagal (M), Kurnool District for a total storage 15.000 to 20.000 TMC including Construction of Spillway, Sluices, Preparation of Detailed Project Report.

Sl. No ProbableQuantity Description of item

Rate in

Rs.

Unit

Amount

(Rs)

1 9413 Ha Conducting Net Levelling as per standard specifications  for  finalising  the  contourcapacity by taking levels at 30 M intervals in foreshore area of  Reservoir for purpose of finalising the contour capacity and fixing

the F.R.L and supply of 6 copies of plans neatly  drawn  duly  noting  ground  profile

contours and F.R.L etc., including cost of drawings, materials, labour charges, rent for instruments and office accommodation,

hire charges of vehicles and  all incidental and operational charges required including

service tax etc., to complete finished item of work including furnishing the Data and Field  Books   etc.,  as   directed  by   the

Engineer-in-charge.

314.94 1 Ha 2964530
2 80 Km Conducting chain survey as per standard specifications including cost of materials, labour charges, rent for instruments and office accommodation, hire charges of vehicles and  all incidental and operational charges required including service tax etc., to complete finished item of work and furnishing the six copies of data and field books etc., as directed by the Engineer-in- charge. 1214.80 1 KM 97184
3 10 Km Taking L.S. at every 25 M intervals as per standard specifications for    Reservoir including    closure  intervals  at  structure locations and supply of six copies of plans neatly drawn including cost of   materials, labour charges, rent for instruments and office accommodation, hire charges of vehicles and  all incidental and operational charges required including service tax etc., to complete finished item of work including furnishing the Data and Field Books etc., as directed by the Engineer-in-charge. 1574.07 1 KM 15741

 

4 70 Km Taking C.S. at every 25 M intervals as per standard  specifications  for     GundrevulaReservoir by chaining  and levels at  3 Mts and closure intervals at structure locations

and supply of six copies of plans neatly drawn and LF Books including cost of materials,    labour    charges,    rent    for

instruments  and  office  accommodation, hire charges of vehicles and  all incidental

and operational charges required including service tax etc.,to complete finished item of  work as  directed  by the  Engineer-in-

charge.

1574.07 1 KM 110185
5 55 Km Carrying B.M. value at every 1/2 KM forReservoir by conducting double check leveling as per standard specifications connecting from G.T.S. and writing the values on permanent structures including cost of  materials, labour charges, rent for instruments  and  office  accommodation, hire charges of vehicles and  all incidental and operational charges required including service tax etc., to carryout the finished item of work as directed by the  Engineer- in-Charge  and  furnishing  six  copies  of DCBM registers excluding cost of stone and fixing charges. 838.81 1 KM 46135
6 1 No Preparation    of    Designs,    ConstructionDrawings and Estimates for the Spillway with N.O.F Dam both sides of Spillway, Scouring Sluices, Earth dam and all appurtenant works for the Reservoir as per ISI Standards CE/CDO guidelines and standard specifications duly adopting the A.P. Revised Standard Data with current S.S.R.   including   all  hydro-mechanical items, EM parts and hoist equipment etc., complete including all materials required including service tax etc., to complete the finished item of work as directed by the department and getting approvals from the competent authority of department for Design & Drawings and supply of 6 copies of    approved designs, drawings and detailed estimates neatly computer typed and binded etc., complete. 600000.00 1 No 600000
7 200 Mts Conducting Sub Soil Exploration as per standard     specifications     along     damalignment and preparation of all required

data and drawings etc., and including logging and preserving the cores, cost of

all     materials  and     all  incidental  and

operational charges  including service tax etc., required to carryout the finished item of work as directed by the  Engineer-in- Charge   and furnishing six copies with Geologist Report.

3000.00 1 Mtr 600000

(contd…Pg-3)

 

 

8 9413 Ha Preparation of contour capacity maps and reservoir capacity tables  as per standardspecifications  with  1  Mtr.  Contour  using

LANDSAT   4   data   and   all   operations required including service tax etc., to carry

out   the   finished   item   of   work   and

furnishing six copies of contour maps and capacity tables and related data, land plan

schedules, R & R plan etc.

60.00 1 Ha 564780

9

338 Nos. Supplying and Fixing of Chainage Stones / Centre Line Stones of size 750X150X150mm including cost and conveyance of Stones with a lead of 35 KM.  and cost of excavation, fixing the stone and refilling

the   excavated   soils   at  site  of  work including    segniorage    charges,    labour

charges and all other incidental and operational charges required for finished item of work as directed by the Engineer-

in-Charge.

59.14 1 No. 19989
10 20 Nos Supplying of Bench Mark Stones of Size750X300X300 mm  and Fixing the same in Cement Concrete M.10 grade using 40mm down size metal   including Cost and conveyance of all materials, machinery, labour with all leads and lifts, watering, curing etc.,  including segniorage charges including  cost  of  excavation,  fixing  the stone in Cement Concrete  and all other incidental and operational charges required for finished item of work as directed by the Engineer-in-Charge. 1004.15 1 No. 20083
11

1

Job Collection of data and preparation of feasibility  reports  and  Detailed  ProjectReport as per CWC norms and furnishing six copies including cost of all materials and  all incidental and operational charges

including service tax etc., required to carryout  the  finished  item  of  work  as

directed by the  Engineer-in-Charge.

200000.00 1 No 200000
12

1

Job Computer   /Software   charges   including computer   operator   charges   and   xeroxcharges.    Including    Service    tax    etc.

Complete for finished item of work.

56000.00 1 Job 56000
13 L.S Provision      for      Tender      Publication, Stationery, Printing, Preparation of TenderSchedules, Agreements etc. 200373

TOTAL:- Rs.5495000/-

(Rupees Fifty Four Lakhs Ninety Five Thousand Only)