1111 Crores for Strengthening of 3437 Government Secondary Schools in AP


The MHRD, Government of India, New Delhi have approved the following civil works in 2011-12, under the scheme of RMSA Phase-III for strengthening of Government Secondary Schools, with total outlay of Rs. 810.41 Crores (Rupees Eight hundred and Ten Crores and Forty One Lakhs only) (75:25 between GoI and Government of A.P.) including MMER @ 2%.of the outlay of the works.

TABLE – I (Rs. In Lakhs)

Sl. No. Activities Area Physical Unit Cost Total Outlay
1 Strengthening         of

3437             existing

Secondary      Schools with             following

components:

1.   Additional classrooms

2.    Science Lab

3.Computer Room

4. Library

5. Art / Craft Room

 

6. Toilet Block

 

7. Drinking     Water facility

 

 

 

 

 

 

 

66

 

66

 

66

100

66

 

 

 

 

 

 

 

4798

 

2260

 

1916

3069

 

3333

1741

 

480

 

 

 

 

 

 

 

4.63

4.60

 

4.60

 

6.75

 

4.60

 

1.00

0.50

 

 

 

 

 

 

 

22214.74

10396.00

 

8813.60

 

20715.75

 

15331.80

1741.00

 

240.00

  Sub-Total   17597 25.68 79452.89
  MMER@2%       1589.06
 

Total

      81041.95

 

The Commissioner & Director of School Education, Hyderabad has, however, vide ref. 5th cited, informed that as per the S.S.R in the year 2012-13 an amount of Rs.1141.93 Crores are required for completion of the above civil works; where as the MHRD, Government of India have sanctioned Rs. 810.41 Crores only. The Commissioner & Director of School Education, Hyderabad have also informed that the M.H.R.D., Government of India have stated vide ref. 3rd cited that State Governments should explore additional financing, if any, from the budget of State Governments only, as to complete the civil works sanctioned in the 11th Five Year Plan. The Commissioner & Director of School Education, Hyderabad has further informed that the Managing Director, A.P. Education & Welfare Infrastructure Development Corporation, Hyderabad has expressed inability to take up works of the above Civil Works with the original unit cost of Government of India, and hence has requested to implement the S.S.R of 2012-2013 for the above works.

3. The Commissioner & Director of School Education, Hyderabad has, therefore, requested the Government to accord necessary administrative approval to take up the above approved civil works with the revised estimated cost of Rs.1141.93 Crores (Rupees Eleven Hundred Forty One Crores and Ninty Three Lakhs Only) including the additional cost of Rs.331.51 Crores, over and above the total outlay of Rs.810.41 Crores approved by the M.H.R.D., Government of India (75:25) from the budget of the State Government. The Commissioner & Director of School Education, Hyderabad has also requested to accord necessary permission to entrust the construction of civil works to the Managing Director, APEWIDC, Hyderabad.

Government, after examination of the above proposal, hereby accord administrative approval to take up the civil works – except the drinking water and toilet blocks – in respect of the 3437 Government Secondary Schools sanctioned under RMSA Phase – III in 2011-2012, with the revised estimated cost of Rs.1111.21 Crores (Rupees One Thousand One hundred and Eleven Crores and Twenty One Lakhs Only) which includes outlay approved by GOI, to a tune of Rs.810.41 Crores, as given in the following Table. Government have also agreed to meet the additional requirement of Rs.300.77 Crores (Rupees Three Hundred Crores and Seventy Seven Lakh Only) from the budget of the State Government in addition to 25% of State share approved by GOI .

Administrative approval is also hereby given to the Commissioner & Director of School Education, Hyderabad to take up the construction of the civil works of the Toilet Blocks and Drinking Water facilities in the above schools, but the unit cost shall be of Rs.1.00 Lakh (Rupees One Lakh Only) and Rs. 0.50 Lakh (Rupees Fifty Thousands Only) respectively, as approved by the G.O.I.

5. Revised outlay approved for construction of Civil Works under RMSA Phase III @ S.S.R. 2012-2013 of State PWD.

TABLE – II (Rs. In Lakhs)

Sl.

 

No.

Name of the component

Physi cal

units

Unit rate in

Lakhs

Total revised out lay for the

works (3X4)

Total

Additional cost to be born by State Governmen t

1

2

3

4

5

6

1

Additional

Class rooms

4798 6.37 30563.26 8348.52
2. Science Lab 2260 6.37 14396.20 4000.2
3. Computer

Room

1916 6.37 12204.92 3390.4

4

Art/Craft room 3333 4.60 21231.21 5899.41

5

Library 3069 6.75 29155.50 8439.75

6

Toilet Block 1741 1.00

1741.00

 

(as provided by GOI)

 

 

7. Drinking water facility 480 0.50

240.00

 

( as provided by GOI)

 

8. MMER @ 2% of the outlay      

 

1589.06

 

 

  TOTAL     111121.15 30077.9

 

Government hereby authorise the Commissioner & Director of School Education, Hyderabad to entrust the construction of the above Civil Works shown in the Table – II in respect of 3437 Secondary Schools approved by the M.H.R.D., Government of India, New Delhi, during the year 2011-12 under RMSA Phase-III, to the Andhra Pradesh Educational Welfare & Infrastructure Development Corporation (APEWIDC), Hyderabad. The Managing Director, APEWIDC, shall take up the works through e-tendering and e-procurement basis and as per the terms and conditions stipulated by the Commissioner & Directorate of School Education, Hyderabad.

The Commissioner and Director of School Education & Ex-Officio Project Director, RMSA, Hyderabad, Andhra Pradesh, shall take necessary further action accordingly.

This order issues with the concurrence of Fin (ESE) Department vide their U.O.No.27272/575/ESE/2013, dated : 31.10.2013

G.O.Ms.No.64 Date : 1.11.2013

1. Lr.No.F.1-44/2011-Sch.1, Dt : 14.09.2011 from Under Secretary to Government of India, MHRD, New Delhi,
2. Lr.No.F.1-29-Sch.1 (A), (B) & (C),  dt  :  14.09.2012 from the Director, RMSA, GOI, MHRD, New Delhi.
3. D.O.Lr.No.1-32/2012, RMSA.I, Dt. 29.11.2012 of MHRD, GoI.
4. G.O.Rt.No.278, Education (SE-Prog.I) Department, dt : 05.02.2013.
5. Lr.Rc.No.261/RMSA/2012,  Dated  16.05.2013,  from  the  C&DSE., Hyderabad.

Leave a comment

Your email address will not be published. Required fields are marked *

This site uses Akismet to reduce spam. Learn how your comment data is processed.