Implementation of Comprehensive water supply services improvements for Armoor Municipality


Orders were issued approving the proposal of DMA, Hyderabad for taking up the projects of drinking water supply sector and under ground sewerage sector for following 13 ULBs under APMDP 1st year procurement plan

Sl.No. Name of the ULB District Name
1. Palasa Kasibugga Srikakulam
2. Markapur Prakasam
3. Guntur Guntur
4. Malkajgiri Ranga Reddy
5. Armoor Nizamabad
6. Kurnool Kurnool
7. Vizianagaram Vizianagaram
8. Kakinada East Godavari
9. Manuguru Khammam
10. Ananthapur Ananthapur
11. Chittoor Chittoor
12. Badvel Kadapa
13 Nellore Nellore

The Commissioner and Director of Municipal Administration, Hyderabad vide reference has submitted that the Andhra Pradesh Municipal Development Project [APMDP] is a World Bank (IBRD Aided) Project and the loan and Project Agreement was concluded on 22nd January 2010 and the Loan No. of the Project is 7816-IN. The total project cost is $350 million (Rs.1670 crores) and the Provision made under component ‘C’ i.e., for Urban Infrastructure Investment is Rs.1461crores

The Commissioner and Director of Municipal Administration, Hyderabad has further submitted that during the Project Steering Committee (PAC) meeting held on 15.10.2012 in the chambers of Secretary to Government (MA) , has approved  sub-project  of  comprehensive  planning  of   water  supply  services improvements in respect of  Armoor Municipality with a total project cost of Rs.114.11 crores and  after

Name of Work Total Estimated Cost

Funding Pattern

70% Grant

20% Loan

10% ULB share
Comprehensive Water Supply Services Improvements for ArmoorMunicipality 114.11

79.88

22.82

11.41

 

 

 

—————————————————————————————————————————————-

Government after careful examination of the proposal and based on the recommendations of Steering Committee and Technical Appraisal communicated by ENC (PH), Hyderabad, hereby accord administrative sanction for Implementation of Comprehensive Planning of water supply services improvements for Armoor Municipality under Andhra Pradesh Municipal Development Project (APMDP) with a total project cost of Rs.114.11 crores with the following funding pattern.

The Secretary, Andhra Pradesh Urban Infrastructure Fund (APUIF), Hyderabad is requested to release the funds to concerned Urban Local Body for implementation of the Project.

The Commissioner , ArmoorMunicipality  shall enter into the loan agreement (MOA) with APUIF and complete the other formalities as per the documents prescribed by the Secretary, APUIF, Hyderabad.

The Commissioner, Armoor Municipality is  directed to implement the concerned Urban Reforms Agenda and submit monthly progress reports to the Secretary, APUIF, Hyderabad and Project Director, APMDP under intimation to Government.

The Commissioner, ArmoorMunicipality shall submit the expenditure particulars and Utilization Certificate and Monthly Progress Reports to Secretary, APUIF. Hyderabad and Project Director, APMDP

The Commissioner and Director of Municipal Administration, Hyderabad, Commissioner, ArmoorMunicipality and Secretary, APUIF, Hyderabad shall take necessary action accordingly.

This order issues with the concurrence of Finance Department vide their U.O. No. 29717/416/A1/Expr.M&F/2012, dated: 5.12.2012.

  1. G.O.Ms.No.288 M.A., dated:21.4.2009
  2. G.O.Rt.No.1222 MA, dated:27.8.2009
  3. Project Appraisal Document, Dated:8.10.2009
  4. From ENC (PH) Lr. No. T7/1/Armoor Mpty/APMDP/2010 Dated 9.8.2012.
  5. Minutes of Project Steering Committee Meeting held on 15.10.2012

6.  From CDMA, Hyderabad Lr.No.T1/118/TU/APMDP/PAC/2012, Dated:19.10. 2012.