Palamuru Ranga Reddy Lift Irrigation Scheme 6.91 Crores Survey Report 1


The  Chief  Engineer(P),  Mahabubnagar  has proposed the Palamuru Ranga Reddy Lift Irrigation Scheme to irrigate an ayacut of about 10.00 lakh acres in Mahabubnagar, Ranga Reddy and Nalgonda districts enroute drinking water to all the villages in three districts by lifting 70 TMC of flood water in 35 days i.e., 2 TMC per day four stages from foreshore of Jurala Project to Padmaram (V), Kondurg (M) near Shadnagar Town (from +310.00m to + 675.00m) which is the higher elevation in between Mahabubnagar and R.R District. The main aim of the scheme is to develop irrigation facility in upland areas & also drinking water facility to enroute villages and water for industrial use.

Palamuru Ranga Reddy Lift Irrigation Scheme 2013

Palamuru Ranga Reddy Lift Irrigation Scheme

The Chief Engineer(P), MBNR has submitted the estimate for an amount of Rs 7.00 Crores for conducting detailed survey and design a Lift Irrigation scheme to serve an ayacut of 10.00 lakh acres to irrigate drought prone areas of Mahabubnagar, Ranga Reddy and Nalgonda districts and supply of drinking water to enroute villages and preparation of Detailed Project Report and design of proposed Palamuru Lift Irrigation Scheme from Foreshore of Jurala Project and requested for according administrative approval at an early date.

View Larger Map
Government after  consideration hereby accord administrative approval to the estimate for an amount of Rs 6.91 Crores (Rupees Six crores ninety one lakhs only) for  conducting  detailed  survey,  investigation and  design  to  prepare Palamuru  Lift Irrigation scheme and identify an ayacut of 10.00 lakh acres to irrigate drought prone areas of Mahabubnagar, Ranga Reddy and Nalgonda districts and supply of drinking water to enroute villages and water for industrial use and prepare a Detailed Project Report of the proposed Palamuru Lift Irrigation Scheme from Foreshore of Jurala Project.

The expenditure shall be debited to the Head of Account MH 4700 -01 Major Irrigation Commercial- MH 145 (MGKLIS)- GH 11 Normal State Plan-SH 27 Canals and Distributaries- 530/531 Other Expenditure.

The Chief Engineer (P), Mahabubnagar shall take necessary action accordingly.

This order issues with the concurrence of Finance (W&P) Department vide their U.O.No.2388/F2(A2)/2013-1, dated 11-07-2013.

If you ask why after statement on  Telangana and just before CM press meet at 7 pm today (08-08-2013).  You Know better….

G.O.Ms.No.72 Dated: 08-08-2013

1) From the CE(P), Mahabubnagar, Lr.No.CE(P)/MBNR/1196, dated 28-08-2012.
2)  From the CE(P), Mahabubnagar, Lr.No.CE(P)/MBNR/Palamuru LIS/1609, dated 29-10-2012.
3) From the CE(P), Mahabubnagar, Lr.No.CE(P)/MBNR/MGKLIS/PLI/168, dated 26-04-2013.
4)  From the CE(P), Mahabubnagar, Lr.No.CE(P)/MBNR/Palamuru LIS/2013/675, dated 27-06-2013.

 