Widening and Strengthening of Telangana Roads 27 works costing 309 Crores


In the combined State of Andhra Pradesh, the Ministry of Road Transport & Highways, Government of India, in their letter 1st read above, have approved 62 works for an amount of Rs.600 crores as Phase I sanction under Central Road Fund (CRF) Scheme, (Out of total 62 works, 31 works costing Rs.306.50 crores pertain to Telangana).  Accordingly, in G.O. 2nd read above, the State Government in the combined State of Andhra Pradesh had accorded administrative sanction for the said works.

Subsequently, in the combined State of Andhra Pradesh, the Ministry of Road Transport & Highways, Government of India, in their letter 3rd read above have approved 51 works costing Rs.600 crores as Phase II sanction under CRF Scheme.  Out of said 51 works, 27 works costing Rs.309.25 crores pertain to Telangana.

Now, after formation of the Telangana State, the E-in-C (R&B), National Highways & CRF, in his letter 4th read above has requested the Government to accord Administrative Sanction for 27 works costing Rs.309.25 crores pertaining to the Telangana State as approved by MoRTH, Govt. of India.

In pursuance of the approval accorded by the Ministry of Roads, Transport and Highways, Govt. of India, Government, hereby accord administrative sanction for 27 works costing Rs.309.50 crores (Rupees Three hundred and Nine Crores and Fifty Lakhs only) as indicated in the Annexure to this order.   The Administrative sanction accorded above is subject to the following conditions:-

The technical and financial sanction to the individual projects shall be accorded within a period of four months from the date of administrative approval of the work failing, which the works will be deemed to have been deleted from the programme.

The period of completion of the projects should not exceed 24 months including period of tendering.

No excess in cost beyond 10% of the amount administratively approved for the proposal will be permissible.  Any excess over 10% will have to be arranged by States from its own resources.

No revised estimate will be considered in the scheme.

Audit shall admit expenditure on the basis of technically approved and financially sanctioned estimate by the State.

No additional fund in excess of the possible allocation of fund as per CRF    Act, 2000 would be allocated to the States.

State Govt., shall ensure that progress of works would not suffer due to delay in payments for want of additional funds under CRF.

Payment of bills in excess of possible allocation of funds, as per CRF Act, 2000, if needed, is to be temporarily arranged by the State Government.

If the projected road merges with any NH, the details of such junction/location shall be got approved from this Ministry/NHAI before entrusting the work.

Display boards should be erected on the sanctioned works.

The State Govt., shall furnish all the relevant details of the roads   considered as per CRF rules i.e., index map showing the area and the proposal, scope / specification of the works in brief, estimated cost of the project based on the actual requirement and proposed starting / completion date etc., and up-gradation of category of roads as per CRF rules prior to taking up the work.

The expenditure on the works sanctioned in para 4 above, shall be met from the head of account “5054–COL on Roads & Bridges; 04–District and Other Roads; MH 800–Other Expenditure, GH (11)–Normal State Plan, SH (04)–Road Development Funds–State Allocation, 530-Major Works; 531 – Other Expenditure”

The Chief Engineer (R&B) Buildings & CRF, Hyderabad shall take necessary action accordingly and also to ensure that there is no financial burden on the State Government on account of improper estimation/investigation of works.

The order issues with the concurrence of the Finance (Expr.PW.II) Department vide their U.O. No.289/14/A1/EBS X/14, Dt:28.06.2014.

ANNEXURE (G.O.Rt.No.3  TR&B (R.I) Dept.  Dated:  28 .06.2014),

CRF( Phase II works)

 

Sl No  District Name of work Scope of work /provisions made in the estimate Job No category of the road cost  in crores
1 3 4 4 5 6 7
    TELANGANA STATE        
1 Adilabad Widening and Strengthening of Bahimsa – Kuber road in Adilabad District Widening and Strengthening CRF-AP-2014-911 MDR 9.00
2 Karimnagar Improvements by Widening and Strenthening to Kamalapur to Ellanthakunta road from Km. 0/0 to 14/553  in Karimnagar District Strengthening & Widening to Double Lane CRF-AP-2014-867 MDR 10.00
3 Karimnagar Improvements by Widening and Strenthening to Peddapally to Kalvasrirampur road from Km 0/0 to 18/3 Strengthening & Widening to Double Lane CRF-AP-2014-872 CAD 10.00
4 Karimnagar Improvements by Widening and Strenthening to Husnabad to Akkanapeta road from Km. 0/0 to 15/4  in Karimnagar District Strengthening & Widening to Double Lane CRF-AP-2014-873 MDR 10.00
5 Mahabubnagar Improvements to Kollapur – Yaparla road from Km.10/750 to 19/4 in Mahabubnagar District Widening and Strengthening CRF-AP-2014-885 MDR 6.25
6 Mahabubnagar Widening and Strengthening of Yerrigera -Ieeza – Alampur road in Mahabubnagar District Widening and Strengthening CRF-AP-2014-912 MDR 9.00
7 Medak Widening and Strengthening to BHEL maingate to meet NH-65 via Tellapur, Velmala and Pati in medak District from Km 2/02 to 19/6 Widening and Strengthening CRF-AP-2014-906 MDR 11.00
8 Medak Widening and Strengthening of Ontimamidi to Karakuthi  in Medak District Widening and Strengthening CRF-AP-2014-909 MDR 9.00
9 Medak Widening and Strengthening of Narayankhed – Shanthipur road in Medak District Widening and Strengthening CRF-AP-2014-910 MDR 10.00
10 Nalgonda Widening and strengthening of Damarcharla to Veerapalem road from Km.0/0 to 15/0 in Nalgonda District. Widening and Strengthening CRF-AP-2014-888 MDR 9.00
11 Nalgonda Widening and Strengtheining of Suryapet to Dosapadu road from Km.0/6 to 12/8 in Nalgonda District. Widening and Strengthening CRF-AP-2014-889 MDR 9.00
12 Nalgonda Widening & Strengthening the carriageway of Thurkapally-Yadagirigutta road from Km 0/0 to 10/0  in Nalgonda District Strengthening & Widening to Double lane CRF-AP-2014-874 MDR 9.00
13 Nalgonda Widening & Strengthening the carriageway of Thorrur- Valgonda road from 30/0 to 43/0 in Nalgonda District Strengthening & Widening to double lane CRF-AP-2014-875 M.D.R. 9.00
14 Nizambad Improvements to Banswada-Uppalwai road Km. 0/0 to 40/3 in Nizamabad District. Widening and Strengthening CRF-AP-2014-895 MDR 25.00
15 Rangareddy Widening & Strengthening to Bommaraspet – Laxmapur Road from Km 13/0 to 31/0 in Rangareddy District. Widening and Strengthening CRF-AP-2014-877 MDR 18.00
16 Rangareddy Improvements to Peerzadiguda – Jodimetla Road from Km 4/0 to 14/4 (work in Km 8/2 to 14/4) in Rangareddy District. Widening and Strengthening CRF-AP-2014-878 MDR 10.00
17 Rangareddy Improvements to Ghatkesar – Anajpur Road from Km 0/0 to 24/0 in Rangareddy District. Widening and Strengthening CRF-AP-2014-879 MDR 20.00
18 Rangareddy Improvements to Aushapur to meet Ghatkesar – Anajpur Road from Km 0/0 to 12/8, and Improvements to Ankushapur to Edulabad Road from Km 0/0 to 4/5 = 4.50 Kms in Rangareddy District. Widening and Strengthening CRF-AP-2014-880 MDR 15.00
19 Rangareddy Improvements / Upgradation to Bahadurpally – Kompally road from Km 0/0 to 7/0 and Secunderabad – Kukatpally road from Km 0/0 to 5/6 and Balanagar – Fathenagar road from Km 0/0 to 1/8 in Rangareddy District. Widening and Strengthening CRF-AP-2014-881 MDR 14.00
20 Rangareddy Improvements / Upgradation from Km 0/0 to 7/4 on Tirumalagiri – Moulali road and Uttamnagar ZTC Road from Km 0/0 to 2/6 and Mirjalguda – Neredmet road from km 0/0 to 5/3 in Rangareddy District. Widening and Strenghening CRF-AP-2014-882 MDR 16.00
21 Rangareddy Widening & strengthening of Kotepalli to morangapally from Km 0/0 to 10/0  in Ranga Reddy District. Widening and Strenghening CRF-AP-2014-896 MDR 10.00
22 Rangareddy Widening & strengthening of Kotepalli to morangapally from Km 10/0 to 20/250  in Ranga Reddy District. Widening and Strenghening CRF-AP-2014-897 MDR 10.00
23 Rangareddy Widening & strengthening of Ekmamidi  to Mehtabkhanguda from Km 10/0 to 7/0 & 13/0 to 17/760 in Ranga Reddy District. Widening and Strenghening CRF-AP-2014-898 MDR 12.00
24 Warangal Strengthening of Chinnapendiyal-Tharrigoppula from km.0/0 to 27/4 in Warangal District Widening and Strenghening CRF-AP-2014-892 MDR 12.00
25 Warangal Widening and strengthening of Mondrai to Palakurthy road from km.0/0 to 16/8 in Warangal District Widening and Strenghening CRF-AP-2014-893 MDR 9.00
26 Warangal Widening and Strengthening of road from Mondrai to Nancharimadugu via Kodakandla in Warangal District Widening and Strenghening CRF-AP-2014-894 MDR 9.00
27 Warangal Widening and Strengthening of Upparapalli X road to Parvathagiri in Warangal District. Widening and Strengthening CRF-AP-2014-913 MDR 9.00
    TWENTY SEVEN WORKS       309.25

AJAY MISRA

PRINCIPAL SECRETARY TO GOVERNMENT

Leave a comment