Secunderabad-Mahabubnagar-Dronachalam Meter guage


Government have released an amount of Rs.29,53,140.62 towards payment of enhanced compensation for the Land acquired for the work “Construction of ROB at Mahabubnagar near the residence of the District Collector at Railway Km 114/7-8 of Secunderabad-Dronachalam meter gauge line in lieu of LC.No.59@ the 113/12-13 between Mahabubnagar-Manyamkonda railway stations in Mahabubnagar District”  under the Head of Account 5054-COL-On Roads & Bridges, 80-General, MH-001-Direction and Administration,GH-11-Normal State Plan, SH(04)-Construction of Roads & Bridges under Railway Safety Works, 530-Major Works, 532-Lands.

E-in-C(R&B),SR&CRN has informed that, the Hon’ble 1st Additional Dist Judge, Mahabubnagar had passed final judgment on 18.01.2012 and enhanced the compensation at Rs.360/- per Sq.yard against the value of Rs.175/- per Sq.yard fixed by the land Acquisition officer/RDO Mahabubnagar. Further the Hon’ble Judge has ordered to pay solatium charges, 12% Additional market value, 9 % Interest and 15% interest on the final rate fixed by the Hon’ble Court.

He has further informed that based on the court orders, the RDO, MBNR has requested the EE(R&B) Mahabubnagar to deposit the funds as per calculations made by the RDO which is amounting to Rs.69,38,488.00 including interest up to 20.11.2014 with 30% solatium, 9% interest from 6.8.1999 to 5.8.1999, 15% interest from 6.8.1999 to 19.11.1999 and 15% interest from 20.11.1999 to 20.11.2014 i.e., 5478 days). Government have released an amount of Rs.29,53,140.62 including interest upto 11-3-2013 .The details are as follows:

  Area Amount
EP.No-20 3517 Sq Yd    Rs.28,76,769.00
EP No-21 3710.4 Sq Yd    Rs.30,34,963.62
EP No-22 1276 Sq yd    Rs.10,26,755.00
  Total =    Rs.69,38,488.00
Amount sanctioned, vide, G.O.Ms.No.9, TR & B (R-1) Dept.,  dt.18-2-2015, _ Rs.29,53,140.62
The amount now to be released     Rs. 39,85,347.38

The Engineer-in-Chief (R&B),SR&CRN has requested the Government to accord administrative sanction for the balance amount of Rs.39,85,347.38(69,38,488-29,53,140.62) in O.P No.3/2007 Dt.18 -1-2012 of 1st Addl. District Judge Mahaboobnagar under the Head of Account 5054-COL – on Roads & Bridges, 80-General, MH-001- Direction and Administration, GH -11- Normal State Plan, SH (04) – Construction of Roads & Bridges under Railway Safety Works, 530- Major works – 532- Lands.

Government, after careful examination of the matter, hereby accord Administrative Sanction for an amount of Rs. 39,85,347.38/- towards payment of balance decretal amount for the Land acquired for the work “Construction of ROB at Mahaboobnagar near the residence of the District Collector at railway km 114/7-8 of Secunderabad-Dronachalam meter guage line in Lieu of L.C.No.59 @ the 113/12-13 between Mahaboobnagar – Manyamkonda Railway Stations in Mahaboobnagar District”.

The expenditure sanctioned in para-5 above shall be debited to the Head of Account 5054-COL-On Roads & Bridges, 80-General, MH-001-Direction and Administration,GH-11-Normal State Plan, SH(04)-Construction of Roads & Bridges under Railway Safety Works, 530-Major Works, 532-Lands.

The Engineer-in-Chief (R&B), SR, RSW & CRN, shall take further action accordingly.

This order issues with the concurrence of Finance (EBS.X) Department vide their U.O.No.7684/233/ A1/EBS.X/2015, Dt.22-6-2015

R & B Department – Sanction of an amount of Rs.39,85,347.38/- towards payment of balance decretal amount for the Land acquired for the work “Construction of ROB at Mahaboobnagar near the residence of the District Collector at railway km 114/7-8 of Secunderabad-Dronachalam meter guage line in Lieu of L.C.No.59 @ the 113/12-13 between Mahaboobnagar – Manyamkonda Railway Stations in Mahaboobnagar District” – Administrative Sanction – Accorded – Orders – Issued.

TRANSPORT, ROADS & BUILDINGS (R-1) DEPARTMENT G.O.Ms.No.Dated:17.11.2015.

1.G.O.Ms.No.9, TR & B (R-1) Dept., dt.18-2-2015,
2.From the E-in-C (R&B), NH, Lr.No.13967/EE(TEC)/DEE2/ AEE1/2013, Dt.14-02-2015,Dt:14.05.2015,Dt:10.09.2015.