Extension of Left Main canal of Rallapadu Project


Extension of left main canal of Rallapadu Project in Lingasamudram (M), Prakasam District from km 3.00 to km 15.875” for an amount of Rs.2144.00 Lakhs and the Engineer-in-Chief, Medium Irrigation, Hyderabad  was also directed to propose for stage-I sanction in the 1st instance, since Survey, Investigation, Designing and land acquisition are involved in the project.

The Engineer-in-Chief, Medium Irrigation, Hyderabad in his letter has submitted a detailed estimate for survey, investigation, design work  and preparation of Detailed Project  Report (DPR) and Land acquisition for the work of “Extension of left main canal of Rallapadu Project in Lingasamudram (M), Prakasam District from km 3.00 to km 15.875” for an amount of Rs.245.25 Lakhs.

The Engineer-in-Chief, Medium Irrigation, Hyderabad has reported that the budget provision for Rallapadu project for the financial year 2012-13 is Rs.750.00 Lakhs and as per the orders issued in G.O. Ms. No. 24, I & CAD (PW-M & MI-R1) dated 30.03.2012, the following stage-I sanction is required for above work:

1)

Amount required for SID operation and preparation of DPR of above work

      Rs. 9.25 Lakhs

2)

Land acquisition for above work

   Rs.236.00 Lakhs

Total      Rs.245.25 Lakhs

In view of the above circumstances, the Engineer-in-Chief, Medium Irrigation, Hyderabad has requested the Government to accord administrative approval for an amount of Rs.245.25 Lakhs to take up stage-I work of Survey,

Investigation, Designs (SID) and preparation of Detailed Project Report (DPR) and Land acquisition for the work “Extension of left main canal of Rallapadu Project in Lingasamudram (M), Prakasam District from km 3.00 to km 15.875” from out of the amount of Rs.2144.00 Lakhs sanctioned in G.O.Ms.No.24,                 I &CAD Department dated 30.03.2012.

After examination of the above proposal, Government accord administrative approval for an amount of Rs. 245.25 Lakhs ( Rupees Two hundred Forty Five Lakhs and Twenty Five Thousand only) to take up stage-I work of  Survey, Investigation, Designs (SID) and preparation of Detailed Project  Report (DPR) and Land acquisition for the work “Extension of left main canal of Rallapadu Project in Lingasamudram (M), Prakasam District from  km 3.00 to km 15.875” from out  of the amount of Rs.2144.00 Lakhs sanctioned in G.O.Ms.No.24, I &CAD Department dated 30.03.2012.

The expenditure sanctioned in Para (5) above shall be debited to the head of account “MH 4701 S.M.J.H.03, MH 195 Reconstruction of Rallapadu Stage-II (V.R.Kota) G.H 11 Normal State Plan – S.H (27) Canals & Distributaries, 530 – Major Works, 531 – Other Expenditure”.

The Engineer-in-Chief, Medium Irrigation, Hyderabad is directed to consider lowest quotation of reputed firm for Survey, Investigation, Designs (SID) using modern methods also and compare and adopt lesser of the two before technical sanction to the estimate.

This order issues with the concurrence of Finance (Expr.P.W) Department vide their U.O.No:26340/910/A1/Expr.P.W/12  dt.01.10.2012.