Construction & Commissioning of Machilipatnam LI Scheme


Vice Chairman & Managing Director, A.P. State Irrigation Development Corporation, A.P., Hyderabad, has stated that the Engineer-in-Chief (AW) has accorded Hydrological clearance for the LI Scheme, on Siva Ganga Major Drain, to feed the Tail end ayacut of 832 acres of Bandar canal to lift 8.32 cusecs of water for Khariff and Rabi for 50% supplementation to the distressed tail end ayacut of Krishna Delta system from Sivaganga Major Drain @ km 6.00 at UT on Bandar Canal. Accordingly the VC & MD APSIDC Ltd., while submitting the DPR has requested the Government to accord administrative approval for an amount of Rs.59.86 lakh for the said work.

Government after examination of the proposal in consultation with the District Collector, Krishna District, Hyderabad, and while returning the estimate, the Vice Chairman & Managing Director, AP State Irrigation Development Corporation Ltd., Hyderabad, has been requested to revise the DPR incorporating the actually available ayacut of 337.01 acres as reported by the Collector, Krishna District, instead of 832 acres proposed in the DPR, vide reference 2nd read above.

The Vice Chairman & Managing Director, AP State Irrigation Development Corporation, Hyderabad, has stated that the detailed project report in respect of Machilipatnam, LI Scheme, is prepared for an amount of Rs.53.90 lakh with Irrigation SSR 2012-13, Cement and Steel rates for the month of July 2012, and the cost per acre is worked out to Rs.13423/- and the works pertaining to Earth work items in respect of Pump House, MS pipe line to Bandar canal and PCC lining to canal costing Rs.0.20 lakh are proposed to be taken up under MGNREGS, and also requested for accord administrative sanction for Machilipantam LI Scheme, on Sivaganga Major Drain @km 6.00 for 50% supplementation to the distressed tail end ayacut of 337.01 acres in Machilipatnam Mandal, of Krishna District, for an amount of Rs.53.90 lakh duly deducting Rs.0.20 lakh under MGNREGS, under Normal State Plan Funds allotted to APSIDC for the year 2012-13 under Head of Account 4702-MH 101-GH(11)-SH(15)-530/531.

Government after examination of the proposal hereby accord administrative approval for an amount of Rs.52.46 lakh (Rupees fifty two lakh and forty six thousand only) for Construction & Commissioning of Machilipatnam LI Scheme, on Sivaganga Major Drain @kn 6.00 to feed the tail end ayacut of Bandar Canal in Machilipatnam Mandal, in Krishna District, out of which an amount of

Rs.52.26 lakh met from Normal State Plan Funds allotted to APSIDC for the year 2012-
13 under Head of Account 4702-MH 101-GH(11)-SH(15)-530/531. The necessary amount of Rs.0.20 lakh for the proposed labour component involved in the
Earth work items in respect of Pump House, MS pipe line to Bandar canal and PCC
lining to canal shall be met from the MGNREGS funds.

The VC &MD APSIDC Ltd., Hyderabad shall take necessary action accordingly.

This order issues with the concurrence of Finance (Exp.PW) Department vide their U.O.No.27831/440/A1/Exp.PW/12, dated 16.10.2012, and PR & RD (RD) Department , U.O.Note 25237/RD.II/A1/2012 PR&RD(RD.II) dated 30.10.2012.